Borgship Tankers v. Product Transport
|
DMC/SandT/05/23 The issue in this case was whether the charterer's claims against the shipowner for loss of a sub-charter freight arising from the ship’s tanks being unfit to carry the contracted cargo of gasoline were claims "arising out of any loss of or damage to or in connection with cargo" within clause 27(c)(ii) of the Shelltime 4 form. If so, then a one-year time bar applied under the Hague-Visby Rules. The judge held that the charterer’s claim did not fall within clause 27(c)(ii) and was not, therefore, time-barred DMC Category Rating: Confirmed This case note is based on an Article in the April 2005 Edition of the ‘Bulletin’, published by the Marine and Insurance teams at the international firm of lawyers, DLA Piper Rudnick Gray Cary. DLA Piper is an International Contributor to this website Background The vessel completed discharge of a cargo of palm oil on 10 April 2002 and proceeded to Amsterdam, where tank cleaning commenced. Notice of readiness was tendered on 19 April but on 20 April, the sub-charterers' surveyors reported that the vessel was not ready to load the intended cargo of gasoline. Further tank cleaning ensued, but by 26 April, the surveyors were still not happy, claiming that the tanks were in poor condition due to the state of the epoxy coating. On 28 April, the parties agreed that the vessel should be redelivered to owners, without prejudice to any existing claims. The charterer claimed against the owner for breach of the charterparty in relation to the condition of the tanks, claiming damages of US$795,000. 97% of the claim was for net freight under the sub-charterparty. The rest was for wasted bunkers and for a balance of account on the final hire statement. The owner, however, argued that the first two claims were time-barred under Clause 27(c)(ii) of the Shelltime form, which provided that any claim (whether brought by charterers or any other person) "arising out of any loss of or damage to or in connection with cargo" would be subject to the Hague-Visby Rules. Article III Rule 6 of those Rules provides: "…the carrier and the ship shall in any event be discharged from all liability whatsoever in respect of the goods unless suit is brought within one year of their delivery or of the date when they should have been delivered". If this provision applied, the goods should have been delivered some time in late April/early May 2003. The arbitration proceedings were not begun until July 2004. The crucial question was whether the claims were claims "arising out of any loss of or damage to or in connection with cargo" within clause 27(c)(ii) of the Shelltime 4 form or claims "in respect of the goods" under Article III Rule 6 of the Hague-Visby rules. The owner argued that the claims all stemmed from uncargoworthiness. The vessel's tanks were not clean enough to receive a particular cargo and, as a result, that cargo was lost. Consequently the time bar applied. The charterer, however, said the claims were for breaches of charter obligations that were independent of the Hague-Visby Rules. According to the decision in The Stena Pacifica [1990] 2 Lloyd's Rep 234, clause 27(c)(ii) of Shelltime 4 did not apply to such claims. Judgment In the present case, no claim was made for loss of or damage to cargo or loss in connection with cargo. The charterer was claiming damages for loss of use of the vessel. The claim was, therefore, not a cargo claim in the sense understood in the marine market so clause 27(c)(ii) and the time bar did not apply. Back to Top
|
These Case Notes have been prepared with care, but neither the Editor nor the International and other Contributors can guarantee that they are free from error, nor that they contain every pertinent point. Reliance should not therefore be placed upon them without independent verification. The Editor and the International and other Contributors disclaim all liability for any loss of whatsoever nature and howsoever arising as a result of others acting or refraining from acting in reliance on the contents of this website and the information to which it gives access. The Editor claims copyright in the content of the website. |