CTI Group v. Transclear
|
Note: on 22 July 2008, the Court of Appeal confirmed the judgment below. To access the note on the Court of Appeal judgment, click here DMC/SandT/08/10 Summary In this case, the Court allowed an appeal from an arbitration award, on the grounds that the risk of failing to provide the contracted cargo under the sale contract fell upon the seller and that no term could be implied into the contract whereby "all bets were off" if a third party intervened (as happened here) to prevent the loading of the contracted cargo DMC Category Rating: Confirmed This note is based on an article written by Alexandra Saxty, a lawyer with the firm of Hill Dickinson in London. The article first appeared in the January 2008 edition of the Hill Dickinson Marine Newsletter The Facts T found an available source of cement at Padang, Indonesia, and the fob contract between T and CTI was finalised. In pursuance of this, CTI ordered the vessel to Padang for loading. However, shortly before arriving off Padang, T terminated the contract. T advised CTI that it was no longer in a position to load the cargo at Padang because "high management" in Jakarta had instructed the shippers not to load the vessel. It appeared that Cemex owned 25% of the supplier’s parent company and had used its power to prevent the suppliers from loading cement onto CTI’s vessel. T subsequently found an alternative supply of cement in Taiwan at a higher price. T remained confident that CTI’s vessel would be loaded successfully, but again suggested that the ship’s documents should show Honduras as the destination. A substitute fob contract was made, and CTI instructed the vessel to sail to Taiwan for loading. While the vessel was en route to Taiwan, T advised CTI that the Taiwanese suppliers were no longer willing to load the cement onto CTI’s vessel and it was therefore ending the parties’ sale arrangements. It was apparent that the suppliers had been pressurised into refusing to load the vessel by another Taiwanese Company which had a major supply contract with Cemex. Neither CTI nor T could find any other available sources of cement in Asia, and in mitigation of its losses CTI instructed the vessel to sail to Novorossiysk (via the Suez Canal) where she was able to load an alternative cargo of cement at a price between the two "failed" contract prices. CTI claimed loss and damage of about US$400,000 arising from T’s breach including (1) loss of time (2) the cost of bags ordered by CTI stamped "Indonesian origin" (3) the difference between the first contract price and the price paid in Novorossiysk (4) the cost of extra bunkers used (5) various additional port expenses and (6) the Suez Canal charges. The Tribunal’s Award
The Award did however provide that had CTI’s claim succeeded, CTI would have been entitled to damages for claims (3) to (6). This was about US$300,000, plus interest. The Tribunal’s decision caused great surprise both on the issue of frustration and on the implied term, all the more so in view of the very small amount of time that had been spent on these matters at the hearing – only about 15 minutes of a 2 day hearing. The defence of frustration is notoriously hard to establish. English law distinguishes between (1) cases where a contract becomes impossible to perform for reasons which are outside the parties’ control (for example, strikes, storms, earthquakes, embargoes) and (2) cases where the contract becomes impossible to perform by reason of something for which one of the parties is responsible. In the first type of case, the contract may be frustrated. However, in the second, it is not. In this case, the cause of the ‘impossibility’ was the refusal of T’s sub-contractor (the cement supplier) to load CTI’s vessel. The contract had therefore become impossible to perform by reason of a matter for which the seller, T, was responsible. The Appeal to the High Court The appeal was on the grounds that the Tribunal's decision on frustration and the implied term was obviously wrong in law, and that no reasonable Tribunal could have made such a decision. One of the points argued on appeal was whether the fault of a supplier could be attributed to a seller where there was no legally binding contract between the seller and the supplier. This was important because a party is not entitled to rely on frustration if the event on which he relies was his fault or responsibility. Counsel for CTI argued that the Tribunal had failed to apply this fundamental principle: the fault of the suppliers (that is, their failure to supply the promised cargo) should be attributed to T, because the suppliers were those to whom T had delegated the performance of the contract with CTI. It was also argued that the fact that there was no binding contract between T and the suppliers did not matter, as the Tribunal had held that the agreement between T and the suppliers was tantamount to a contract. What mattered was whether or not T had engaged or arranged to use a particular supplier. On this, Mr Justice Field disagreed, and held that the default of a supplier can only be attributed to a seller where there is a legal obligation between the seller and the supplier. As the Tribunal had found that there was no such legal obligation, CTI failed on that point. However, Mr Justice Field did agree that, as a matter of law, the contract had not been frustrated. He held that once it had been found that the contract was impossible to perform, the key question was whether the risk of failure of supply was on the sellers or on the buyers. In this case the risk was with the sellers, and the Award was wrong. The judge made the following points:-
Mr Justice Field also held that neither of the two contracts could be said to contain the supposed implied term, as it was "fundamentally inconsistent with the effect of the contract’s express terms". Furthermore, the term was not necessary to give the contract business efficacy, or so obvious that either it went without saying or should be implied as a matter of law. Appeal to the Court of Appeal T then sought permission to appeal to the Court of Appeal. This was granted, but only on the issue of frustration. The appeal is due to be heard in June 2008. Comment Back to Top |
These Case Notes have been prepared with care, but neither the Editor nor the International and other Contributors can guarantee that they are free from error, nor that they contain every pertinent point. Reliance should not therefore be placed upon them without independent verification. The Editor and the International and other Contributors disclaim all liability for any loss of whatsoever nature and howsoever arising as a result of others acting or refraining from acting in reliance on the contents of this website and the information to which it gives access. The Editor claims copyright in the content of the website. |