Lansat Shipping v. Glencore Grain (The "Paragon")
|
Note: the decision in this case has been upheld by the Court of Appeal in a judgment delivered on 31 July 2009. To access the note of the Court of Appeal judgment, click here DMC/SandT/09/04 Michael Davey (instructed by Ince & Co) for the Appellant, Lansat ("the Owners")Simon Birt (instructed by Birketts LLP) for the Respondent, Glencore ("the Charterers") CHARTERPARTIES: LATE REDELIVERY: ILLEGITIMATE LAST VOYAGE: PENALTY CLAUSES: GENUINE PRE-ESTIMATE OF DAMAGES Summary A clause which provided for the hire rate for the final 30 days of the timecharter period to be increased to the higher prevailing market rate upon late redelivery of the vessel beyond the final terminal date of the charter period amounted to a penalty and was consequently unenforceable under English law, as the clause’s primary purpose was to act as a deterrent to late redelivery by the charterers and not as a genuine pre-estimate of damage resulting from the breach of contract. Note contributed by Jim Leighton, BSc (Hons), LLB (Hons), LLM (Maritime Law), Trainee Solicitor and International Contributor to DMC’s CaseNotes. The Charterers paid hire at the charter rate for the duration of the charter up until the last redelivery date on 14 May 2007 and at the market rate for the 6.166 days the vessel was overdue. The Owners also claimed hire based on the market rate for thirty days before the latest date for redelivery in reliance on clause 101 of the charter, which stated: "The Charterers hereby undertake the obligation/responsibility to make thorough investigations and every arrangement in order to ensure that the last voyage of this Charter will in no way exceed the maximum period under this Charter Party. If, however, Charterers fail to comply with this obligation and the last voyage will exceed the maximum period, should the market rise above the Charter Party rate in the meantime, it is hereby agreed that the charter hire will be adjusted to reflect the prevailing market level from the 30th day prior to the maximum period [d]ate until actual redelivery of the vessel to the Owners." At this time, hire rates were rising, so the additional claim was at a market rate of US$46,083.82 per day, as opposed to the charter rate of US$29,500 per day. On this basis, the Owners claimed US$471,603.32 over and above what the Charterers had already paid. Only one question arose for decision in this case, which came by way of appeal under s.69 of the Arbitration Act 1996 from an LMAA arbitration award on a preliminary issue (made by Michael Baker-Harber, Alan Burbidge and Robert Gaisford), which was whether or not clause 101 of the charter was a penalty. The LMAA tribunal had found in favour of the Charterers that it was. Judgment Given that the contract was a timecharter, the relevance of legitimate and illegitimate final voyage orders came into play, which was an issue the Judge duly analysed. In the former, charterers give orders for the employment of the vessel which can reasonably be expected to be performed by the time for redelivery; in the latter, charterers give orders for employment which cannot reasonably be expected to be performed by the charter’s final terminal date. In the former, charterers are obliged to compensate in damages for the late redelivery at the charter rate or, if higher, the market rate for the overrun period; in the latter, charterers’ conduct amounts to a repudiation of the contract which owners may accept as bringing the charter to an end, whereupon owners can go out into the market to seek a new fixture, though in such circumstances owners suffered no loss. But, as the Charterers pointed out and with which the Judge agreed, if Owners nevertheless choose to comply with an illegitimate final voyage order leading to late redelivery, the resulting loss at law would be the same as if there had been a late redelivery following compliance with a legitimate final voyage order. In such circumstances, the Owners had not lost the opportunity of an early redelivery; they had instead chosen not to take that chance by following the Charterers’ orders. The Judge pointed out that while the Owners were correct to submit that the comparison of the liquidated damages was to be made with the upper end of the range of the loss which may be suffered, the pre-estimate must nevertheless be a genuine pre-estimate of recoverable loss for the breach of the contract in question. The fact that in broad terms the potential loss of the Owners may be considered different and greater was not in point if such loss was irrecoverable in law. It followed that, whether the Charterers’ final voyage orders were legitimate or illegitimate, the Owners had suffered no legally recoverable loss in the nature of that provided for by clause 101 of the charter. As a result, clause 101 did not provide a genuine pre-estimate of recoverable damages, so amounted to a penalty and therefore was unenforceable. Comment However, given the Judge’s analysis of the relevance of legitimate and illegitimate voyages and the interplay of losses which are and are not legally recoverable at common law, there could well be room for charterers now to argue that any clause which seeks to alter the result in The "Achilleas" ought to be struck down as a penalty. Such arguments would need to be tempered by reference to the principle of freedom of contract and the distinction between a clause that is drafted such as to be a true penalty and that which is legitimately negotiated between owners and charterers to be a true reflection of real (though not necessarily legally recoverable) losses that may flow from a late redelivery caused by illegitimate final voyage orders. It is also arguable that the Judge’s reasoning should be limited to the context in which it was made, namely a clause which specified a fixed period before the final terminal date of the charter without distinction between legitimate and illegitimate final voyage orders. As Chitty on Contracts makes clear (2008 ed. at para.
26-125, fn. 655 and the cases there cited), an agreed sum may take account of
loss likely to be suffered which may not fall within the normal remoteness test.
This indicates that the Judge’s distinction between recoverable and
irrecoverable loss at common law is not an absolute and determinative
proposition of law when considering whether a clause is a penalty. In each case
it is a matter of degree as to whether or not a sum that may or would be too
remote at common law to recover is liquidated damages or a penalty. |
These Case Notes have been prepared with care, but neither the Editor nor the International and other Contributors can guarantee that they are free from error, nor that they contain every pertinent point. Reliance should not therefore be placed upon them without independent verification. The Editor and the International and other Contributors disclaim all liability for any loss of whatsoever nature and howsoever arising as a result of others acting or refraining from acting in reliance on the contents of this website and the information to which it gives access. The Editor claims copyright in the content of the website. |